INSPECTION & ACCEPTANCE
First Article Inspection for Mold Inserts: What to Check Before Approval
A receiving checklist for buyers and mold engineers who need to decide whether a first component is ready for approval.

A first article inspection for a mold insert should connect the delivered part to the approved drawing, the inspected characteristics and the supporting material records. Before approving it, check that every agreed requirement has a result or a clearly identified outstanding action. A report full of green cells can still leave an important requirement unanswered.
For buyers ordering custom precision mold inserts, the useful output is an approval decision that another engineer can trace. The review sequence below separates the identity of the part, coverage of the specification and disposition of any exceptions.
Key takeaways
- Match the inspected part, drawing revision and material records before reviewing individual values.
- Track dimensions, drawing notes and other agreed requirements in one coverage list.
- Keep unmeasured items and deviations visible until the responsible person resolves them.
- Agree what first-article approval authorizes for subsequent parts.
1. What should first article inspection establish?
First article inspection checks an initial manufactured part or sample against its design requirements. Hexagon describes a process built around an inspection plan, numbered drawing characteristics and a report linking those requirements to results. That linkage matters more than the particular software used to produce the document. Source: Hexagon’s introduction to FAI.
For a mold component order, agree the scope before manufacture. Identify the parts to be inspected, the manufacturing condition to be evaluated and the records to be supplied. A first-piece check during rough machining answers a different question from acceptance of a finished, hardened and polished insert.
Also distinguish customer approval from permission to continue production. If the supplier must wait for approval before producing the remaining quantity, put that hold point in the order. An emailed report should not leave either party guessing whether production may proceed.
2. Confirm the part and revision first
Start with the report header, drawing and physical identification. The part number, revision and quantity represented by the inspection should agree across the package. If they do not, resolve the mismatch before evaluating dimensions.
- Part identity: identify which delivered component or sample the report covers.
- Drawing authority: confirm the current 2D drawing, associated 3D model and applicable specifications.
- Manufacturing condition: state whether treatment, coating, grinding and polishing are complete.
- Set identity: distinguish individual inserts, cavity positions and matched components where applicable.
A shared drawing does not make every component in a set the inspected first article. If one sample represents a batch, record that sampling agreement. If each part requires its own critical-feature results, make the individual identification visible.
3. Build a requirement-to-evidence checklist
Review coverage before reviewing pass/fail status. A useful checklist includes every requirement in the agreed scope, including drawing notes that may not produce a CMM number. Numbering the characteristics gives both teams a stable way to discuss missing or disputed evidence.
Dimensions and geometry
Link each characteristic to the nominal requirement, limits, applicable datum references, measured result and inspection method. Preserve the drawing’s units and geometric meaning.
Material and condition
Link the specified grade and source to the relevant material document. Treat the heat-treatment record and final hardness result as separate evidence where required.
Working surfaces
Identify finish zones, edge requirements and any approved appearance reference. A general visual acceptance does not replace a specified roughness measurement.
Assembly requirements
Record any agreed fit trial or matched-part check separately. Name the mating component and test condition so that the result can be interpreted later.
The checklist is an editorial review aid, not a universal reporting standard. Adapt it to the purchase order and drawing. SENLAN’s manufacturing and quality overview describes the available inspection context; the actual report scope needs to be agreed for the component.
4. Read the result together with its method
A measured value becomes useful when it can be connected to the characteristic being accepted. Check whether the method can reach the surface or feature, whether the stated references match the drawing and whether the result represents the final condition.
For example, a bore diameter result does not automatically establish its position relative to a locating face. A material certificate does not establish the finished component’s hardness. A polished appearance does not establish the numerical surface texture requirement.
If two laboratories disagree, use the separate guide to resolving CMM inspection differences. Keep this first-article review focused on whether the evidence package covers the agreed requirements, rather than treating a disagreement as an automatic supplier failure.
5. Keep open items visible
Separate “accepted,” “outside requirement” and “not yet verified.” These conditions require different decisions. An unmeasured feature must remain open even if all the completed measurements are within their limits.
Illustrative review, not a SENLAN inspection record
A package contains a dimensional report for an insert, a source-material document and a note that final polishing is still outstanding. The buyer can review the completed dimensions, but should not silently treat that package as acceptance of the finished surface.
The open-item record should name the affected surface, the missing evidence, the person responsible and the next review point. If polishing could affect an agreed working dimension, the release plan should identify the relevant final check.
For a deviation, request a documented disposition: rework and reinspect, replace, or seek a customer-approved concession. Record who has authority to approve the decision. Do not rewrite the drawing limit inside the report to make the measured result appear acceptable.
6. Is an AS9102 report always required?
Use the reporting standard required by the customer’s contract. SAE identifies AS9102C as an aerospace first article inspection standard whose requirements complement customer requirements. Its existence does not make an aerospace-format report mandatory for every mold insert order. Source: SAE AS9102C scope.
If a customer specifies AS9102 or another formal procedure, confirm the applicable revision and deliverables before quotation. If no formal standard is specified, agree a clear report format and coverage list instead of assuming both parties mean the same thing by “FAI.”
7. Close the approval with a repeat-order baseline
The approval record should identify the accepted part, revision, evidence package and any remaining conditions. It should also state whether approval releases the balance of the order, a trial assembly or only a particular manufacturing stage.
Preserve that baseline for repeat work. When the drawing, material condition or manufacturing route changes, review which evidence needs to be repeated. Hexagon lists design and process changes among situations that can trigger another first-article review; the order-specific trigger should be agreed between buyer and supplier. Source: Hexagon FAI guidance.
Define the inspection package with the drawing
Send SENLAN the component drawing, revision, quantity and required inspection documents. Mark the characteristics that control assembly and state whether approval is required before the remaining parts are made.